REKAP BANTUAN DANA LINGKUNGAN (BDL) TINGKAT DESA / KELURAHAN

Status Tanggal : 01 Januari 2012

Jenis Infrastruktur Volume Biaya Status Selesai
Kota : BANTUL
Kecamatan : BAMBANG LIPURO
Desa / Kelurahan : SIDOMULYO
1. Jalan - Cor Beton/Blok 494.00 200,000,000.00 Ya
Total   200,000,000.00
Kecamatan : BANGUNTAPAN
Desa / Kelurahan : JAGALAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 2.00 48,000,000.00 Ya
3. Jalan - Cor Beton/Blok 553.00 36,000,000.00 Ya
4. Jalan - Paving Blok 220.00 10,000,000.00 Ya
5. Sumur Resapan, SPAH 50.00 50,000,000.00 Ya
Total   150,000,000.00
Desa / Kelurahan : JAMBIDAN
1. BOP 1.00 6,000,000.00 Ya
2. Talud 607.00 166,000,000.00 Ya
Total   172,000,000.00
Desa / Kelurahan : WIROKERTEN
1. Jembatan 1.00 136,000,000.00 Tidak
Total   136,000,000.00
Kecamatan : BANTUL
Desa / Kelurahan : RINGIN HARJO
1. Gorong-Gorong 32.00 10,250,000.00 Ya
2. Jalan 875.00 43,750,000.00 Ya
3. Talud 100.00 14,000,000.00 Ya
Total   68,000,000.00
Desa / Kelurahan : SABDODADI
1. Dam/Bendungan 54.00 40,000,000.00 Ya
2. Jalan 260.00 38,000,000.00 Ya
3. Talud 200.00 22,000,000.00 Ya
Total   100,000,000.00
Desa / Kelurahan : TRIRENGGO
1. Drainase, Selokan, SAH, SAL 220.50 61,000,000.00 Ya
2. Jalan - Cor Beton/Blok 112.50 49,000,000.00 Ya
3. Talud 36.75 10,000,000.00 Ya
Total   120,000,000.00
Kecamatan : IMOGIRI
Desa / Kelurahan : IMOGIRI
1. BOP 1.00 6,000,000.00 Ya
2. Gorong-Gorong 12.00 2,004,000.00 Ya
3. Jalan 476.00 51,354,000.00 Ya
4. Jalan - Cor Beton/Blok 1,500.00 50,250,000.00 Ya
5. Sanitasi, MCK 18.00 2,004,000.00 Ya
6. Talud 120.00 4,380,000.00 Ya
7. Tutup Saluran 48.00 4,008,000.00 Ya
Total   120,000,000.00
Desa / Kelurahan : SRIHARJO
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 2,000.00 116,400,000.00 Ya
3. Sanitasi, MCK 7.00 47,600,000.00 Ya
Total   170,000,000.00
Kecamatan : JETIS
Desa / Kelurahan : CANDEN
1. BOP 1.00 4,932,500.00 Ya
2. Drainase, Selokan, SAH, SAL 185.00 18,739,000.00 Ya
3. Jalan - Cor Beton/Blok 1,954.60 67,029,000.00 Ya
4. Other 6.00 6,060,000.00 Ya
5. Talud 980.00 79,239,500.00 Ya
Total   176,000,000.00
Desa / Kelurahan : SUMBER AGUNG
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 49.00 14,000,000.00 Ya
Total   20,000,000.00
Desa / Kelurahan : TRIMULYO
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 3,200.00 114,000,000.00 Ya
Total   120,000,000.00
Kecamatan : KASIHAN
Desa / Kelurahan : BANGUNJIWO
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 2,193.00 153,525,000.00 Ya
3. Jembatan 1.00 22,675,000.00 Ya
4. Sanitasi, MCK 1.00 17,800,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : NGESTIHARJO
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 875.00 159,000,000.00 Ya
3. Sanitasi, MCK 5.00 20,000,000.00 Ya
4. Talud 85.00 15,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : TAMANTIRTO
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 1,775.00 49,500,000.00 Ya
3. Jalan - Cor Beton/Blok 3,946.00 104,500,000.00 Ya
Total   160,000,000.00
Kecamatan : KRETEK
Desa / Kelurahan : DONOTIRTO
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 50.00 3,750,000.00 Ya
3. Gorong-Gorong 9.00 2,980,000.00 Ya
4. Jalan 709.00 158,245,000.00 Ya
5. Talud 75.00 25,025,000.00 Ya
Total   196,000,000.00
Kecamatan : PANDAK
Desa / Kelurahan : GILANGHARJO
1. Jalan - Cor Beton/Blok 5,606.00 114,700,000.00 Ya
2. Sanitasi, MCK 10.00 25,000,000.00 Ya
3. Talud 5,606.00 10,300,000.00 Ya
Total   150,000,000.00
Desa / Kelurahan : WIJIREJO
1. Jalan - Cor Beton/Blok 4,219.00 81,000,000.00 Ya
2. Jalan - Makadam 600.00 13,400,000.00 Ya
3. Pasar, Fasilitas Perdagangan 1.00 60,000,000.00 Ya
4. Puskesmas, Posyandu, Fasilitas Kesehatan 2.00 28,000,000.00 Ya
5. Talud 150.00 13,400,000.00 Ya
Total   195,800,000.00
Kecamatan : PIYUNGAN
Desa / Kelurahan : SITIMULYO
1. Balai Pertemuan 850.00 30,000,000.00 Ya
2. BOP 1.00 6,000,000.00 Ya
3. Drainase, Selokan, SAH, SAL 500.00 46,800,000.00 Ya
4. Gorong-Gorong 4.50 4,000,000.00 Ya
5. Jalan 1,622.00 78,600,000.00 Ya
6. Talud 52.50 14,600,000.00 Ya
Total   180,000,000.00
Desa / Kelurahan : SRIMARTANI
1. Air Bersih, Reservoar, Broncapturing 1,200.00 9,895,000.00 Ya
2. Balai Pertemuan 1.00 9,605,000.00 Ya
3. Drainase, Selokan, SAH, SAL 750.00 20,250,000.00 Ya
4. Drainase, Selokan, SAH, SAL 300.00 10,500,000.00 Ya
5. Jalan 300.00 10,875,000.00 Ya
6. Jalan 300.00 10,875,000.00 Ya
7. Jalan - Cor Beton/Blok 100.00 5,800,000.00 Ya
8. Jalan - Cor Beton/Blok 500.00 14,000,000.00 Ya
9. Jalan - Cor Beton/Blok 400.00 11,200,000.00 Ya
10. Jalan - Cor Beton/Blok 400.00 11,200,000.00 Ya
11. Jalan - Cor Beton/Blok 600.00 13,800,000.00 Ya
12. Talud 250.00 9,000,000.00 Ya
13. Talud 250.00 9,000,000.00 Ya
14. Talud 200.00 9,000,000.00 Ya
15. Talud 700.00 16,200,000.00 Ya
16. Talud 500.00 18,000,000.00 Ya
17. Talud 300.00 10,800,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : SRIMULYO
1. Balai Pertemuan 1.00 12,800,000.00 Ya
2. Gorong-Gorong 10.00 6,000,000.00 Ya
3. Irigasi 50.00 14,800,000.00 Ya
4. Jalan 300.00 7,000,000.00 Ya
5. Jalan 200.00 4,000,000.00 Ya
6. Jalan 300.00 8,000,000.00 Ya
7. Jalan 500.00 12,800,000.00 Ya
8. Jalan 100.00 6,000,000.00 Ya
9. Jalan 100.00 12,800,000.00 Ya
10. Jalan 300.00 6,000,000.00 Ya
11. Jalan - Cor Beton/Blok 100.00 12,800,000.00 Ya
12. Jalan - Cor Beton/Blok 100.00 12,800,000.00 Ya
13. Jalan - Cor Beton/Blok 100.00 12,800,000.00 Ya
14. Jalan - Cor Beton/Blok 100.00 6,000,000.00 Ya
15. Jalan - Cor Beton/Blok 100.00 7,000,000.00 Ya
16. Jalan - Cor Beton/Blok 100.00 12,800,000.00 Ya
17. Jembatan 1.00 6,000,000.00 Ya
18. Sanitasi, MCK 2.00 6,000,000.00 Ya
19. Talud 25.00 6,000,000.00 Ya
20. Talud 25.00 12,800,000.00 Ya
21. Talud 25.00 7,800,000.00 Ya
22. Talud 25.00 7,000,000.00 Ya
Total   200,000,000.00
Kecamatan : PUNDONG
Desa / Kelurahan : SELOHARJO
1. Air Bersih, Reservoar, Broncapturing 500.00 10,500,000.00 Ya
2. Dam/Bendungan 1.00 10,750,000.00 Ya
3. Drainase, Selokan, SAH, SAL 48.00 10,576,880.00 Ya
4. Jalan - Cor Beton/Blok 286.00 95,508,400.00 Ya
5. Jembatan 1.00 10,140,000.00 Ya
6. Sanitasi, MCK 1.00 9,090,000.00 Ya
7. Talud 130.00 21,434,720.00 Ya
Total   168,000,000.00
Desa / Kelurahan : SRIHARDONO
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 1,600.00 36,000,000.00 Ya
3. Jalan - Cor Beton/Blok 5,600.00 140,000,000.00 Ya
4. Jalan - Makadam 800.00 8,000,000.00 Ya
5. Jalan - Paving Blok 2,000.00 10,000,000.00 Ya
Total   200,000,000.00
Kecamatan : SANDEN
Desa / Kelurahan : GADINGSARI
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 580.00 130,480,000.00 Ya
3. Jembatan 1.00 10,525,000.00 Ya
4. Talud 550.00 38,995,000.00 Ya
Total   186,000,000.00
Desa / Kelurahan : MURTIGADING
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 120.00 23,762,000.00 Ya
3. Jalan 370.00 83,510,695.00 Ya
4. Sanitasi, MCK 1.00 3,101,000.00 Ya
5. Talud 107.00 73,626,305.00 Ya
Total   190,000,000.00
Desa / Kelurahan : SRIGADING
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 446.00 27,600,000.00 Ya
3. Jalan - Cor Beton/Blok 649.00 147,000,000.00 Ya
4. Talud 113.00 19,400,000.00 Ya
Total   200,000,000.00
Kecamatan : SEDAYU
Desa / Kelurahan : ARGOREJO
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 72.00 20,168,200.00 Ya
3. Gorong-Gorong 2.00 462,600.00 Ya
4. Jalan 1,771.00 35,554,200.00 Ya
5. Jalan - Cor Beton/Blok 206.00 104,586,600.00 Ya
6. Talud 131.00 33,228,400.00 Ya
Total   200,000,000.00
Kecamatan : SEWON
Desa / Kelurahan : BANGUNHARJO
1. BOP 1.00 6,000,000.00 Ya
2. Dam/Bendungan 140.00 28,000,000.00 Ya
3. Jalan 7,375.00 89,000,000.00 Ya
4. Jalan - Cor Beton/Blok 2,625.00 22,000,000.00 Ya
5. Talud 307.00 11,000,000.00 Ya
Total   156,000,000.00
Desa / Kelurahan : PANGGUNGHARJO
1. Irigasi 1,600.00 60,000,000.00 Ya
2. Jalan 9,000.00 100,000,000.00 Ya
3. Jembatan 1.00 20,000,000.00 Ya
Total   180,000,000.00
Kecamatan : SRANDAKAN
Desa / Kelurahan : PONCOSARI
1. BOP 1.00 5,813,950.00 Ya
2. Jalan - Cor Beton/Blok 265.00 152,098,150.00 Ya
3. Talud 25.00 12,087,900.00 Ya
Total   170,000,000.00
Desa / Kelurahan : TRIMURTI
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 265.00 21,451,000.00 Ya
3. Jalan - Cor Beton/Blok 889.00 155,882,000.00 Ya
4. Sanitasi, MCK 2.00 16,667,000.00 Ya
Total   200,000,000.00
Kota : GUNUNG KIDUL
Kecamatan : GEDANG SARI
Desa / Kelurahan : HARGO MULYO
1. Air Bersih, Reservoar, Broncapturing 12.00 64,100,000.00 Ya
2. Balai Pertemuan 1.00 60,000,000.00 Ya
3. BOP 1.00 6,000,000.00 Ya
4. Gorong-Gorong 4.00 2,000,000.00 Ya
5. Jalan - Cor Beton/Blok 50.00 5,000,000.00 Ya
6. Jalan - Cor Beton/Blok 100.00 7,500,000.00 Ya
7. Jembatan 1.00 2,100,000.00 Ya
8. Jembatan 1.00 4,000,000.00 Ya
9. Jembatan 1.00 3,500,000.00 Ya
10. Sanitasi, MCK 2.00 44,300,000.00 Ya
11. Talud 5.00 1,500,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : NGALANG
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 112.00 13,208,500.00 Ya
3. Talud 448.00 180,791,500.00 Ya
Total   200,000,000.00
Kecamatan : NGLIPAR
Desa / Kelurahan : NGLIPAR
1. BOP 1.00 6,000,000.00 Ya
2. Gorong-Gorong 5.00 4,000,000.00 Ya
3. Jalan - Cor Beton/Blok 384.00 158,000,000.00 Ya
4. Sanitasi, MCK 24.00 12,000,000.00 Ya
5. Talud 80.00 20,000,000.00 Ya
Total   200,000,000.00
Kecamatan : PALIYAN
Desa / Kelurahan : KARANG ASEM
1. Jalan 1.00 29,800,000.00 Ya
2. Jalan 1.00 23,812,000.00 Ya
3. Jembatan 1.00 146,388,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : KARANG DUWET
1. Drainase, Selokan, SAH, SAL 800.00 53,772,500.00 Ya
2. Jalan 900.00 19,270,000.00 Ya
3. Jalan 400.00 19,082,500.00 Ya
4. Jalan - Cor Beton/Blok 1,345.00 107,875,000.00 Ya
Total   200,000,000.00
Kecamatan : PANGGANG
Desa / Kelurahan : GIRIHARJO
1. Air Bersih, Reservoar, Broncapturing 3.00 15,000,000.00 Ya
2. BOP 1.00 6,000,000.00 Ya
3. Drainase, Selokan, SAH, SAL 650.00 25,000,000.00 Ya
4. Gorong-Gorong 46.00 49,000,000.00 Ya
5. Jalan - Cor Beton/Blok 200.00 15,000,000.00 Ya
6. Other 1.00 90,000,000.00 Ya
Total   200,000,000.00
Kecamatan : SAPTO SARI
Desa / Kelurahan : KEPEK
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 359.00 37,400,000.00 Ya
3. Jalan - Cor Beton/Blok 1,650.00 156,600,000.00 Ya
Total   200,000,000.00
Kota : KLATEN
Kecamatan : CEPER
Desa / Kelurahan : CETAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 320.00 37,000,000.00 Ya
3. Drainase, Selokan, SAH, SAL 152.00 20,000,000.00 Ya
4. Jalan 1,360.00 30,000,000.00 Ya
5. Jalan 1,150.00 30,000,000.00 Ya
6. Jalan - Cor Beton/Blok 1,260.00 30,000,000.00 Ya
7. Jalan - Cor Beton/Blok 1,050.00 33,000,000.00 Ya
8. Jalan - Cor Beton/Blok 318.00 10,000,000.00 Ya
Total   196,000,000.00
Desa / Kelurahan : DLIMAS
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 75.00 5,827,000.00 Ya
3. Gorong-Gorong 14.00 35,302,000.00 Ya
4. Jalan - Cor Beton/Blok 210.00 6,777,000.00 Ya
5. Jalan - Cor Beton/Blok 375.00 12,102,000.00 Ya
6. Jalan - Cor Beton/Blok 180.00 5,809,000.00 Ya
7. Jalan - Cor Beton/Blok 391.00 12,594,000.00 Ya
8. Jalan - Cor Beton/Blok 300.00 9,682,000.00 Ya
9. Jalan - Cor Beton/Blok 150.00 4,841,000.00 Ya
10. Jalan - Cor Beton/Blok 300.00 9,682,000.00 Ya
11. Jalan - Cor Beton/Blok 175.00 5,647,000.00 Ya
12. Sanitasi, MCK 1.00 11,548,000.00 Ya
13. Talud 41.00 11,606,000.00 Ya
14. Talud 57.00 16,940,000.00 Ya
15. Talud 116.00 32,554,000.00 Ya
16. Talud 32.00 8,857,000.00 Ya
17. Talud 15.00 4,232,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : JAMBU KIDUL
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 400.00 15,000,000.00 Ya
3. Jalan 1,200.00 24,000,000.00 Ya
4. Jalan - Cor Beton/Blok 1,050.00 15,000,000.00 Ya
5. Jalan - Cor Beton/Blok 1,050.00 15,000,000.00 Ya
6. Jalan - Cor Beton/Blok 1,137.50 19,000,000.00 Ya
7. Jalan - Cor Beton/Blok 1,050.00 15,000,000.00 Ya
8. Jalan - Cor Beton/Blok 1,050.00 15,000,000.00 Ya
9. Jalan - Cor Beton/Blok 1,102.50 17,000,000.00 Ya
10. Jalan - Cor Beton/Blok 1,300.00 21,000,000.00 Ya
11. Talud 78.75 17,000,000.00 Ya
12. Talud 87.50 13,000,000.00 Ya
Total   192,000,000.00
Desa / Kelurahan : KAJEN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 735.00 9,880,000.00 Ya
3. Jalan - Cor Beton/Blok 1,480.00 124,968,000.00 Ya
4. Sanitasi, MCK 1.00 1,650,000.00 Ya
5. Talud 718.05 53,502,000.00 Ya
Total   196,000,000.00
Desa / Kelurahan : KUNCEN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 900.00 35,867,000.00 Ya
3. Jalan 1,400.00 42,363,000.00 Ya
4. Jalan - Cor Beton/Blok 225.00 6,637,000.00 Ya
5. Jalan - Cor Beton/Blok 1,230.00 36,283,000.00 Ya
6. Jalan - Cor Beton/Blok 300.00 8,849,000.00 Ya
7. Jalan - Cor Beton/Blok 450.00 13,274,000.00 Ya
8. Jalan - Cor Beton/Blok 390.00 10,619,000.00 Ya
9. Jalan - Cor Beton/Blok 350.00 10,324,000.00 Ya
10. Jalan - Cor Beton/Blok 360.00 11,504,000.00 Ya
11. Talud 130.00 18,280,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : MEGER
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 18.00 53,307,500.00 Ya
3. Jalan - Cor Beton/Blok 31.25 11,380,500.00 Ya
4. Jalan - Cor Beton/Blok 795.00 11,714,000.00 Ya
5. Jalan - Cor Beton/Blok 412.50 29,042,000.00 Ya
6. Jembatan 1.00 12,647,000.00 Ya
7. Jembatan 1.00 14,754,500.00 Ya
8. Jembatan 1.00 12,708,900.00 Ya
9. Talud 84.80 25,520,400.00 Ya
10. Talud 61.50 16,537,200.00 Ya
11. Talud 21.00 6,388,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : PASUNGAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 100.00 6,531,000.00 Ya
3. Jalan 15.96 17,398,000.00 Ya
4. Jalan - Cor Beton/Blok 874.00 25,588,000.00 Ya
5. Jalan - Cor Beton/Blok 750.00 17,546,000.00 Ya
6. Jalan - Cor Beton/Blok 500.00 14,617,000.00 Ya
7. Jalan - Cor Beton/Blok 375.00 8,806,000.00 Ya
8. Jalan - Cor Beton/Blok 360.00 11,405,000.00 Ya
9. Jembatan 1.00 8,235,000.00 Ya
10. Talud 183.75 42,074,000.00 Ya
11. Talud 48.75 9,693,000.00 Ya
12. Talud 70.00 10,766,000.00 Ya
13. Talud 19.50 8,077,000.00 Ya
14. Talud 42.41 6,632,000.00 Ya
15. Talud 19.50 6,632,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : POKAK
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 594.33 19,181,000.00 Ya
3. Jalan - Cor Beton/Blok 300.00 9,682,000.00 Ya
4. Jalan - Cor Beton/Blok 825.00 26,626,000.00 Ya
5. Jalan - Cor Beton/Blok 675.00 21,784,000.00 Ya
6. Jalan - Cor Beton/Blok 675.00 21,784,000.00 Ya
7. Jalan - Cor Beton/Blok 750.00 24,205,000.00 Ya
8. Talud 10.00 3,533,000.00 Ya
9. Talud 150.00 14,401,000.00 Ya
10. Talud 155.00 24,002,000.00 Ya
11. Talud 130.00 28,802,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : SREBEGAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 500.00 15,533,000.00 Ya
3. Jalan - Cor Beton/Blok 375.00 12,102,000.00 Ya
4. Jalan - Cor Beton/Blok 412.50 13,313,000.00 Ya
5. Jalan - Cor Beton/Blok 250.00 8,068,000.00 Ya
6. Jalan - Cor Beton/Blok 375.00 12,102,000.00 Ya
7. Jalan - Cor Beton/Blok 426.00 13,748,000.00 Ya
8. Jalan - Cor Beton/Blok 250.00 8,068,000.00 Ya
9. Jalan - Cor Beton/Blok 155.00 5,002,000.00 Ya
10. Talud 200.00 13,218,000.00 Ya
11. Talud 150.00 10,244,000.00 Ya
12. Talud 77.55 22,140,000.00 Ya
13. Talud 165.00 11,235,000.00 Ya
14. Talud 150.00 5,948,000.00 Ya
15. Talud 18.52 10,147,000.00 Ya
16. Talud 100.00 16,523,000.00 Ya
17. Talud 100.00 6,609,000.00 Ya
Total   190,000,000.00
Kecamatan : GANTIWARNO
Desa / Kelurahan : BATURAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 5,880.00 188,000,000.00 Ya
Total   194,000,000.00
Desa / Kelurahan : CEPORAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 347.00 46,700,000.00 Ya
3. Sumur Suntik 300.00 131,300,000.00 Ya
Total   184,000,000.00
Desa / Kelurahan : GENTAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 3,790.50 122,334,000.00 Ya
3. Jalan - Makadam 120.00 3,414,000.00 Ya
4. Talud 244.00 68,252,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : GESIKAN
1. BOP 1.00 6,000,000.00 Ya
2. Talud 1,000.00 194,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : JABUNG
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 38.00 1,900,000.00 Ya
3. Drainase, Selokan, SAH, SAL 125.00 5,185,000.00 Ya
4. Jalan - Cor Beton/Blok 130.00 3,500,000.00 Ya
5. Jalan - Cor Beton/Blok 738.00 27,787,000.00 Ya
6. Jalan - Cor Beton/Blok 150.00 3,100,000.00 Ya
7. Jalan - Cor Beton/Blok 620.00 20,009,000.00 Ya
8. Jalan - Cor Beton/Blok 150.00 4,500,000.00 Ya
9. Jalan - Cor Beton/Blok 336.00 10,844,000.00 Ya
10. Jalan - Cor Beton/Blok 374.50 14,216,000.00 Ya
11. Jalan - Cor Beton/Blok 600.00 19,364,000.00 Ya
12. Jalan - Paving Blok 636.00 30,395,000.00 Ya
13. Talud 38.00 8,200,000.00 Ya
14. Talud 60.00 7,000,000.00 Ya
Total   162,000,000.00
Desa / Kelurahan : KARANGTURI
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 720.00 92,909,000.00 Ya
3. Jalan - Makadam 720.00 56,148,000.00 Ya
4. Talud 183.00 16,353,000.00 Ya
5. Talud 500.00 28,590,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : KATEKAN
1. BOP 1.00 6,000,000.00 Ya
2. Box/Plat Decker 1.00 10,000,000.00 Ya
3. Box/Plat Decker 1.00 10,000,000.00 Ya
4. Jalan 3,200.00 80,000,000.00 Ya
5. Jalan - Cor Beton/Blok 480.00 12,790,000.00 Ya
6. Jembatan 1.00 5,000,000.00 Ya
7. Talud 330.00 76,210,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : KERTEN
1. BOP 1.00 714,500.00 Ya
2. Drainase, Selokan, SAH, SAL 150.00 15,930,000.00 Ya
3. Drainase, Selokan, SAH, SAL 11.00 1,407,000.00 Ya
4. Jalan - Cor Beton/Blok 186.00 16,387,000.00 Ya
5. Jalan - Cor Beton/Blok 275.00 23,190,000.00 Ya
6. Jalan - Cor Beton/Blok 67.00 6,728,500.00 Ya
7. Jalan - Cor Beton/Blok 227.00 24,798,000.00 Ya
8. Jalan - Cor Beton/Blok 200.00 18,727,000.00 Ya
9. Jalan - Cor Beton/Blok 293.00 24,651,500.00 Ya
10. Jalan - Cor Beton/Blok 67.00 6,092,500.00 Ya
11. Jalan - Cor Beton/Blok 275.00 25,939,000.00 Ya
12. Jalan - Cor Beton/Blok 190.00 20,234,000.00 Ya
13. Talud 40.00 5,251,000.00 Ya
14. Talud 15.00 5,158,000.00 Ya
15. Talud 18.00 4,792,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : KRAGILAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 300.00 20,000,000.00 Ya
3. Jalan - Cor Beton/Blok 700.00 52,000,000.00 Ya
4. Jembatan 2.00 44,000,000.00 Ya
5. Talud 550.00 40,000,000.00 Ya
Total   162,000,000.00
Desa / Kelurahan : MLESE
1. BOP 1.00 6,000,000.00 Ya
2. Gorong-Gorong 6.00 2,600,000.00 Ya
3. Jalan - Cor Beton/Blok 1,000.00 32,600,000.00 Ya
4. Jalan - Cor Beton/Blok 600.00 19,000,000.00 Ya
5. Jalan - Cor Beton/Blok 437.50 14,000,000.00 Ya
6. Jalan - Cor Beton/Blok 765.00 19,000,000.00 Ya
7. Jalan - Paving Blok 540.00 36,800,000.00 Ya
8. Talud 280.00 28,000,000.00 Ya
9. Talud 75.00 9,000,000.00 Ya
10. Talud 175.00 17,000,000.00 Ya
Total   184,000,000.00
Desa / Kelurahan : MURUH
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 172.00 16,026,000.00 Ya
3. Jalan - Cor Beton/Blok 200.00 18,383,000.00 Ya
4. Jalan - Cor Beton/Blok 196.00 17,838,000.00 Ya
5. Jalan - Cor Beton/Blok 265.00 23,878,000.00 Ya
6. Jalan - Cor Beton/Blok 300.00 27,147,000.00 Ya
7. Talud 37.00 5,276,000.00 Ya
8. Talud 184.00 25,246,000.00 Ya
9. Talud 85.00 11,762,000.00 Ya
10. Talud 100.00 13,922,000.00 Ya
11. Talud 100.00 13,896,000.00 Ya
12. Talud 150.00 20,626,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : MUTIHAN
1. BOP 1.00 6,000,000.00 Ya
2. Gorong-Gorong 60.00 11,500,000.00 Ya
3. Jalan - Cor Beton/Blok 3,500.00 137,000,000.00 Ya
4. Talud 60.00 3,500,000.00 Ya
Total   158,000,000.00
Desa / Kelurahan : SAWIT
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 861.70 64,000,000.00 Ya
3. Jalan - Cor Beton/Blok 480.80 35,708,000.00 Ya
4. Jalan - Cor Beton/Blok 300.00 22,280,000.00 Ya
5. Jalan - Cor Beton/Blok 494.50 36,724,000.00 Ya
6. Jembatan 4.00 19,488,000.00 Ya
7. Talud 102.00 15,800,000.00 Ya
Total   200,000,000.00
Kecamatan : JOGONALAN
Desa / Kelurahan : BAKUNG
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 2,350.00 104,525,000.00 Ya
3. Jalan 420.00 18,880,000.00 Ya
4. Talud 238.00 70,595,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : DOMPYONGAN
1. BOP 1.00 5,940,000.00 Ya
2. Jalan - Cor Beton/Blok 600.00 12,102,000.00 Ya
3. Jalan - Cor Beton/Blok 600.00 19,364,000.00 Ya
4. Jalan - Cor Beton/Blok 375.00 19,364,000.00 Ya
5. Jalan - Makadam 330.00 8,842,000.00 Ya
6. Jalan - Makadam 600.00 15,882,000.00 Ya
7. Talud 19.88 29,344,000.00 Ya
8. Talud 69.94 36,209,000.00 Ya
9. Talud 21.11 29,611,000.00 Ya
10. Talud 6.94 23,342,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : GONDANGAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 1,080.00 52,500,000.00 Ya
3. Jalan - Cor Beton/Blok 1,116.00 29,067,000.00 Ya
4. Jalan - Cor Beton/Blok 150.00 5,388,000.00 Ya
5. Jalan - Cor Beton/Blok 702.00 23,070,000.00 Ya
6. Jalan - Cor Beton/Blok 651.00 21,021,000.00 Ya
7. Talud 26.45 5,252,000.00 Ya
8. Talud 21.74 3,947,000.00 Ya
9. Talud 50.11 9,755,000.00 Ya
Total   156,000,000.00
Desa / Kelurahan : JOTON
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 200.00 5,878,400.00 Ya
3. Jalan - Cor Beton/Blok 120.00 7,130,500.00 Ya
4. Jalan - Cor Beton/Blok 187.00 6,690,600.00 Ya
5. Jalan - Cor Beton/Blok 3,480.00 92,300,500.00 Ya
Total   118,000,000.00
Desa / Kelurahan : KARANGDUKUH
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 2,045.00 75,924,000.00 Ya
3. Talud 164.00 37,388,000.00 Ya
4. Talud 324.00 80,688,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : KRAGUMAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 945.00 103,600,000.00 Ya
3. Jalan 630.00 20,000,000.00 Ya
4. Jalan 1,260.00 12,110,000.00 Ya
5. Jalan - Paving Blok 2,875.00 58,290,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : NGERING
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 1,040.00 30,014,000.00 Ya
3. Jalan - Cor Beton/Blok 600.00 19,364,000.00 Ya
4. Jalan - Cor Beton/Blok 880.00 28,320,000.00 Ya
5. Talud 43.40 12,909,000.00 Ya
6. Talud 364.00 103,393,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : PAKAHAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 849.00 36,316,000.00 Ya
3. Jalan - Cor Beton/Blok 307.50 9,316,000.00 Ya
4. Jalan - Cor Beton/Blok 466.80 14,143,000.00 Ya
5. Jalan - Cor Beton/Blok 130.00 3,938,500.00 Ya
6. Jalan - Cor Beton/Blok 536.90 16,266,000.00 Ya
7. Jalan - Cor Beton/Blok 390.00 11,816,000.00 Ya
8. Jalan - Cor Beton/Blok 427.50 12,952,000.00 Ya
Total   110,747,500.00
Desa / Kelurahan : PLAWIKAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 150.00 17,900,000.00 Ya
3. Drainase, Selokan, SAH, SAL 300.00 21,876,000.00 Ya
4. Drainase, Selokan, SAH, SAL 400.00 25,112,000.00 Ya
5. Drainase, Selokan, SAH, SAL 100.00 8,484,000.00 Ya
6. Drainase, Selokan, SAH, SAL 150.00 13,443,000.00 Ya
7. Drainase, Selokan, SAH, SAL 150.00 14,000,000.00 Ya
8. Drainase, Selokan, SAH, SAL 179.00 8,902,000.00 Ya
9. Jalan 350.00 11,668,000.00 Ya
10. Jalan - Cor Beton/Blok 200.00 21,070,000.00 Ya
11. Jalan - Cor Beton/Blok 150.00 8,539,000.00 Ya
12. Talud 400.00 26,045,000.00 Ya
13. Talud 87.00 12,961,000.00 Ya
Total   196,000,000.00
Desa / Kelurahan : PRAWATAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 450.00 25,000,000.00 Ya
3. Jalan - Cor Beton/Blok 700.00 5,000,000.00 Ya
4. Jalan - Cor Beton/Blok 364.00 4,000,000.00 Ya
5. Jalan - Cor Beton/Blok 210.00 6,777,120.00 Ya
6. Jalan - Cor Beton/Blok 350.00 9,000,000.00 Ya
7. Jalan - Cor Beton/Blok 200.00 6,454,400.00 Ya
8. Jembatan 1.00 8,500,000.00 Ya
9. Talud 35.90 4,000,000.00 Ya
10. Talud 15.00 2,222,880.00 Ya
11. Talud 18.00 2,045,600.00 Ya
12. Talud 39.20 9,000,000.00 Ya
13. Talud 19.80 4,000,000.00 Ya
Total   92,000,000.00
Desa / Kelurahan : REJOSO
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 2,200.00 84,360,000.00 Ya
3. Talud 533.00 107,640,000.00 Ya
Total   198,000,000.00
Desa / Kelurahan : SOMOPURO
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 22.30 16,000,000.00 Ya
3. Jalan 110.50 19,000,000.00 Ya
4. Jalan 58.50 18,000,000.00 Ya
5. Jalan - Cor Beton/Blok 60.20 15,000,000.00 Ya
6. Jalan - Cor Beton/Blok 75.00 16,000,000.00 Ya
7. Jalan - Paving Blok 66.90 16,500,000.00 Ya
8. Jalan - Paving Blok 80.30 19,000,000.00 Ya
9. Talud 131.50 19,000,000.00 Ya
10. Talud 111.12 19,000,000.00 Ya
11. Talud 175.35 18,500,000.00 Ya
Total   182,000,000.00
Desa / Kelurahan : SUMYANG
1. BOP 1.00 6,000,000.00 Ya
2. Gorong-Gorong 21.00 13,072,900.00 Ya
3. Jalan 575.00 30,962,100.00 Ya
4. Jalan 1,050.00 54,012,200.00 Ya
5. Jalan - Cor Beton/Blok 754.00 27,546,200.00 Ya
6. Jalan - Cor Beton/Blok 540.00 25,449,600.00 Ya
7. Talud 168.00 25,345,000.00 Ya
8. Talud 160.85 17,612,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : TAMBAKAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 600.00 15,231,000.00 Ya
3. Jalan - Cor Beton/Blok 50.00 14,393,000.00 Ya
4. Jalan - Cor Beton/Blok 600.00 16,793,000.00 Ya
5. Jalan - Cor Beton/Blok 50.00 12,761,000.00 Ya
6. Jalan - Cor Beton/Blok 750.00 17,136,000.00 Ya
7. Jalan - Cor Beton/Blok 450.00 13,464,000.00 Ya
8. Jalan - Cor Beton/Blok 600.00 17,683,000.00 Ya
9. Jalan - Cor Beton/Blok 300.00 9,133,000.00 Ya
10. Jalan - Cor Beton/Blok 450.00 14,225,000.00 Ya
11. Jalan - Cor Beton/Blok 300.00 12,090,500.00 Ya
12. Jalan - Cor Beton/Blok 600.00 14,794,000.00 Ya
13. Jalan - Cor Beton/Blok 300.00 8,911,000.00 Ya
14. Jalan - Cor Beton/Blok 750.00 17,927,500.00 Ya
15. Jalan - Cor Beton/Blok 300.00 9,458,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : TANGKISAN POS
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 2,292.00 116,642,000.00 Ya
3. Talud 121.22 41,658,000.00 Ya
Total   164,300,000.00
Desa / Kelurahan : TITANG
1. BOP 1.00 6,000,000.00 Ya
2. Gorong-Gorong 50.00 5,056,000.00 Ya
3. Jalan 543.00 24,725,000.00 Ya
4. Jalan 58.80 2,677,000.00 Ya
5. Jalan 86.80 3,952,000.00 Ya
6. Jalan 78.40 3,569,000.00 Ya
7. Jalan 131.60 5,992,000.00 Ya
8. Jalan 89.60 4,079,000.00 Ya
9. Jalan 414.00 19,124,000.00 Ya
10. Jalan - Cor Beton/Blok 705.00 24,710,000.00 Ya
11. Jalan - Cor Beton/Blok 352.80 12,434,500.00 Ya
12. Talud 54.16 12,863,000.00 Ya
13. Talud 37.45 9,610,000.00 Ya
14. Talud 58.17 14,141,000.00 Ya
15. Talud 90.00 15,067,500.00 Ya
Total   164,000,000.00
Desa / Kelurahan : WONOBOYO
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 1,092.00 47,083,000.00 Ya
3. Jalan 400.00 48,603,400.00 Ya
4. Jalan 1,059.50 17,681,750.00 Ya
5. Talud 60.00 24,221,500.00 Ya
6. Talud 36.00 15,098,850.00 Ya
7. Talud 30.00 9,340,000.00 Ya
8. Talud 60.00 7,600,000.00 Ya
9. Talud 60.00 24,371,500.00 Ya
Total   200,000,000.00
Kecamatan : KALIKOTES
Desa / Kelurahan : GEMBLEGAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 200.00 12,000,000.00 Ya
3. Drainase, Selokan, SAH, SAL 240.00 10,000,000.00 Ya
4. Jalan 116.00 7,000,000.00 Ya
5. Jalan 180.00 11,000,000.00 Ya
6. Jalan 312.50 12,000,000.00 Ya
7. Jalan 148.00 9,000,000.00 Ya
8. Jalan - Cor Beton/Blok 500.00 10,000,000.00 Ya
9. Jalan - Cor Beton/Blok 402.00 12,000,000.00 Ya
10. Jalan - Cor Beton/Blok 500.00 10,000,000.00 Ya
11. Jalan - Cor Beton/Blok 300.00 9,000,000.00 Ya
12. Talud 20.80 8,000,000.00 Ya
13. Talud 133.00 38,750,000.00 Ya
14. Talud 84.00 10,000,000.00 Ya
15. Talud 36.00 12,000,000.00 Ya
16. Talud 46.80 11,250,000.00 Ya
Total   188,000,000.00
Desa / Kelurahan : JIMBUNG
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 2,140.00 62,000,000.00 Ya
3. Talud 340.00 88,000,000.00 Ya
Total   156,000,000.00
Desa / Kelurahan : JOGOSETRAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 197.00 15,110,000.00 Ya
3. Drainase, Selokan, SAH, SAL 30.00 1,950,000.00 Ya
4. Drainase, Selokan, SAH, SAL 99.00 6,490,000.00 Ya
5. Drainase, Selokan, SAH, SAL 27.00 2,000,000.00 Ya
6. Drainase, Selokan, SAH, SAL 64.50 5,022,000.00 Ya
7. Jalan 342.00 16,700,000.00 Ya
8. Jalan - Cor Beton/Blok 540.00 16,042,000.00 Ya
9. Jalan - Cor Beton/Blok 102.00 3,030,000.00 Ya
10. Jalan - Cor Beton/Blok 594.00 17,646,000.00 Ya
11. Jalan - Cor Beton/Blok 204.00 6,060,000.00 Ya
12. Jalan - Cor Beton/Blok 272.70 8,101,000.00 Ya
13. Jalan - Cor Beton/Blok 587.50 17,453,000.00 Ya
14. Jalan - Cor Beton/Blok 318.60 9,464,000.00 Ya
15. Jalan - Cor Beton/Blok 555.00 16,487,000.00 Ya
16. Sanitasi, MCK 1.00 6,445,000.00 Ya
17. Talud 59.38 17,000,000.00 Ya
18. Talud 56.38 16,000,000.00 Ya
19. Talud 45.88 13,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : KALIKOTES
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 275.55 17,225,000.00 Ya
3. Jalan 1,350.00 62,152,000.00 Ya
4. Jalan - Cor Beton/Blok 2,875.00 85,909,000.00 Ya
5. Talud 72.19 20,714,000.00 Ya
Total   192,000,000.00
Desa / Kelurahan : KRAJAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 590.00 35,631,000.00 Ya
3. Jalan 100.00 33,523,000.00 Ya
4. Jalan - Cor Beton/Blok 3,244.00 104,721,000.00 Ya
5. Talud 229.01 20,125,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : NGEMPLAK
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 1,530.00 42,840,000.00 Ya
3. Jalan 3,174.00 127,000,000.00 Ya
4. Jalan - Cor Beton/Blok 204.00 8,160,000.00 Ya
Total   184,000,000.00
Desa / Kelurahan : TAMBONGWETAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 240.00 18,132,000.00 Ya
3. Jalan - Cor Beton/Blok 210.00 20,130,000.00 Ya
4. Jalan - Cor Beton/Blok 230.00 16,610,000.00 Ya
5. Jalan - Cor Beton/Blok 200.00 9,673,000.00 Ya
6. Jembatan 1.00 21,029,000.00 Ya
7. Talud 78.00 13,927,000.00 Ya
8. Talud 190.00 21,708,000.00 Ya
9. Talud 300.00 17,500,000.00 Ya
10. Talud 230.00 16,151,000.00 Ya
11. Talud 170.00 23,402,000.00 Ya
12. Talud 240.00 15,738,000.00 Ya
Total   200,000,000.00
Kecamatan : KEBONARUM
Desa / Kelurahan : BASIN
1. BOP 1.00 6,000,000.00 Ya
2. Talud 146.70 42,000,000.00 Ya
Total   48,000,000.00
Desa / Kelurahan : GONDANG
1. BOP 1.00 6,000,000.00 Ya
2. Gorong-Gorong 14.00 5,446,000.00 Ya
3. Jalan - Cor Beton/Blok 450.00 11,558,500.00 Ya
4. Jalan - Cor Beton/Blok 195.00 4,965,000.00 Ya
5. Jalan - Cor Beton/Blok 150.00 3,844,000.00 Ya
6. Jalan - Cor Beton/Blok 147.50 4,173,000.00 Ya
7. Jalan - Cor Beton/Blok 150.00 4,200,000.00 Ya
8. Jalan - Cor Beton/Blok 300.00 6,727,000.00 Ya
9. Jalan - Cor Beton/Blok 270.00 5,766,000.00 Ya
10. Jalan - Cor Beton/Blok 225.00 6,424,000.00 Ya
11. Jalan - Cor Beton/Blok 225.00 5,302,000.00 Ya
12. Jalan - Cor Beton/Blok 300.00 6,727,000.00 Ya
13. Jalan - Cor Beton/Blok 300.00 6,727,000.00 Ya
14. Jalan - Cor Beton/Blok 180.00 5,766,000.00 Ya
15. Talud 22.00 5,774,300.00 Ya
16. Talud 21.00 5,567,000.00 Ya
17. Talud 17.50 4,651,800.00 Ya
18. Talud 21.00 5,662,000.00 Ya
19. Talud 15.40 4,310,300.00 Ya
20. Talud 735.00 19,376,000.00 Ya
21. Talud 9.00 2,517,500.00 Ya
22. Talud 9.00 2,466,600.00 Ya
23. Talud 30.00 8,049,000.00 Ya
Total   142,000,000.00
Desa / Kelurahan : KARANGDUREN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 25.00 3,500,000.00 Ya
3. Drainase, Selokan, SAH, SAL 26.25 2,250,000.00 Ya
4. Jalan 7,380.00 3,500,000.00 Ya
5. Jalan 600.00 5,000,000.00 Ya
6. Jalan 600.00 3,500,000.00 Ya
7. Jalan 300.00 2,250,000.00 Ya
8. Jalan 625.00 3,500,000.00 Ya
9. Jalan - Cor Beton/Blok 900.00 5,600,000.00 Ya
10. Jalan - Cor Beton/Blok 600.00 2,100,000.00 Ya
11. Jalan - Cor Beton/Blok 350.00 4,000,000.00 Ya
12. Jalan - Cor Beton/Blok 900.00 3,500,000.00 Ya
13. Jalan - Cor Beton/Blok 4,500.00 5,500,000.00 Ya
14. Jalan - Cor Beton/Blok 400.00 4,500,000.00 Ya
15. Jalan - Cor Beton/Blok 750.00 6,000,000.00 Ya
16. Jembatan 1.00 24,000,000.00 Ya
17. Talud 48.00 5,800,000.00 Ya
18. Talud 96.00 3,500,000.00 Ya
19. Talud 80.00 3,500,000.00 Ya
20. Talud 162.00 3,500,000.00 Ya
Total   101,000,000.00
Desa / Kelurahan : MALANGJIWAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 200.00 29,290,000.00 Ya
3. Jalan 1,050.00 16,824,000.00 Ya
4. Jalan - Cor Beton/Blok 175.00 10,431,000.00 Ya
5. Jalan - Cor Beton/Blok 500.00 5,217,000.00 Ya
6. Jalan - Cor Beton/Blok 140.00 3,088,750.00 Ya
7. Jalan - Cor Beton/Blok 437.50 3,722,000.00 Ya
8. Jalan - Cor Beton/Blok 171.50 4,211,000.00 Ya
9. Jalan - Cor Beton/Blok 327.00 6,047,500.00 Ya
10. Jalan - Cor Beton/Blok 600.00 24,516,000.00 Ya
11. Jalan - Cor Beton/Blok 90.00 2,339,500.00 Ya
12. Jalan - Cor Beton/Blok 277.20 8,292,000.00 Ya
13. Jalan - Cor Beton/Blok 157.50 3,210,850.00 Ya
14. Jalan - Cor Beton/Blok 247.50 15,428,000.00 Ya
15. Jalan - Cor Beton/Blok 143.50 2,393,500.00 Ya
16. Jalan - Cor Beton/Blok 330.00 10,304,000.00 Ya
17. Jalan - Cor Beton/Blok 750.00 10,341,000.00 Ya
18. Jalan - Cor Beton/Blok 112.50 2,562,400.00 Ya
19. Talud 36.72 9,311,000.00 Ya
20. Talud 32.76 11,401,405.00 Ya
21. Talud 23.40 3,278,000.00 Ya
22. Talud 26.64 5,872,770.00 Ya
23. Talud 17.28 3,918,325.00 Ya
Total   198,000,000.00
Desa / Kelurahan : MENDEN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 3,240.00 116,681,300.00 Ya
3. Jalan - Cor Beton/Blok 1,599.00 54,691,000.00 Ya
4. Jembatan 1.00 9,232,200.00 Ya
5. Talud 56.00 13,395,500.00 Ya
Total   200,000,000.00
Desa / Kelurahan : PLUNENG
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 3,800.00 152,000,000.00 Ya
3. Talud 168.00 42,000,000.00 Ya
Total   200,000,000.00
Kecamatan : NGAWEN
Desa / Kelurahan : CANDI REJO
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 78.00 3,500,000.00 Ya
3. Drainase, Selokan, SAH, SAL 78.00 3,500,000.00 Ya
4. Drainase, Selokan, SAH, SAL 78.00 3,500,000.00 Ya
5. Drainase, Selokan, SAH, SAL 90.00 3,500,000.00 Ya
6. Drainase, Selokan, SAH, SAL 90.00 3,500,000.00 Ya
7. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
8. Jalan - Cor Beton/Blok 225.00 7,500,000.00 Ya
9. Jalan - Cor Beton/Blok 130.00 4,950,000.00 Ya
10. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
11. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
12. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
13. Jalan - Cor Beton/Blok 130.00 4,950,000.00 Ya
14. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
15. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
16. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
17. Jalan - Cor Beton/Blok 164.00 6,450,000.00 Ya
18. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
19. Jalan - Cor Beton/Blok 130.00 4,950,000.00 Ya
20. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
21. Jalan - Cor Beton/Blok 130.00 4,950,000.00 Ya
22. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
23. Jalan - Cor Beton/Blok 164.00 6,450,000.00 Ya
24. Jalan - Cor Beton/Blok 120.00 4,450,000.00 Ya
25. Jalan - Cor Beton/Blok 130.00 4,950,000.00 Ya
26. Jembatan 1.00 3,400,000.00 Ya
27. Jembatan 1.00 3,400,000.00 Ya
28. Jembatan 1.00 3,400,000.00 Ya
29. Jembatan 1.00 3,300,000.00 Ya
30. Sanitasi, MCK 1.00 3,200,000.00 Ya
31. Sanitasi, MCK 1.00 2,900,000.00 Ya
32. Sanitasi, MCK 1.00 2,900,000.00 Ya
33. Sanitasi, MCK 1.00 2,900,000.00 Ya
34. Sanitasi, MCK 1.00 2,900,000.00 Ya
35. Talud 17.10 4,400,000.00 Ya
36. Talud 17.10 4,400,000.00 Ya
37. Talud 17.10 4,400,000.00 Ya
38. Talud 18.00 4,500,000.00 Ya
39. Talud 17.10 4,400,000.00 Ya
40. Talud 17.10 5,400,000.00 Ya
41. Talud 17.10 4,400,000.00 Ya
42. Talud 17.10 4,400,000.00 Ya
43. Talud 17.10 4,400,000.00 Ya
44. Talud 18.00 4,500,000.00 Ya
45. Talud 17.10 4,400,000.00 Ya
46. Talud 18.00 4,500,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : DRONO
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 600.00 21,514,500.00 Ya
3. Jalan 1,200.00 82,810,000.00 Ya
4. Jalan - Cor Beton/Blok 8,400.00 89,675,500.00 Ya
Total   200,000,000.00
Desa / Kelurahan : KWAREN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 910.00 89,000,000.00 Ya
3. Jalan - Cor Beton/Blok 977.00 105,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : MAYUNGAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 2,622.00 114,750,000.00 Ya
3. Jalan - Cor Beton/Blok 2,400.00 54,000,000.00 Ya
4. Talud 101.25 25,250,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : PEPE
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 750.00 9,375,000.00 Ya
3. Talud 890.50 184,625,000.00 Ya
Total   200,000,000.00
Kecamatan : PEDAN
Desa / Kelurahan : BEJI
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 900.00 29,046,000.00 Ya
3. Jalan - Cor Beton/Blok 660.00 21,033,000.00 Ya
4. Jalan - Cor Beton/Blok 525.00 16,943,000.00 Ya
5. Jalan - Cor Beton/Blok 900.00 29,046,000.00 Ya
6. Jalan - Cor Beton/Blok 450.00 14,523,000.00 Ya
7. Talud 109.00 32,497,000.00 Ya
8. Talud 76.00 21,832,000.00 Ya
9. Talud 93.00 27,080,000.00 Ya
Total   198,000,000.00
Desa / Kelurahan : BENDO
1. BOP 1.00 6,000,000.00 Ya
2. Box/Plat Decker 1.00 7,383,000.00 Ya
3. Drainase, Selokan, SAH, SAL 600.00 32,774,000.00 Ya
4. Drainase, Selokan, SAH, SAL 200.00 10,924,000.00 Ya
5. Jalan - Cor Beton/Blok 900.00 12,858,000.00 Ya
6. Jalan - Cor Beton/Blok 180.00 10,286,000.00 Ya
7. Jalan - Cor Beton/Blok 750.00 21,430,000.00 Ya
8. Jalan - Cor Beton/Blok 300.00 11,143,000.00 Ya
9. Sanitasi, MCK 1.00 6,445,000.00 Ya
10. Talud 56.00 14,300,000.00 Ya
11. Talud 100.00 10,328,000.00 Ya
12. Talud 300.00 34,083,000.00 Ya
13. Talud 75.00 7,746,000.00 Ya
14. Talud 56.00 14,300,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : JATIMULYO
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 1,755.00 12,610,000.00 Ya
3. Jalan 90.00 5,075,000.00 Ya
4. Jalan 300.00 29,418,000.00 Ya
5. Jalan - Cor Beton/Blok 337.50 10,000,000.00 Ya
6. Jalan - Cor Beton/Blok 420.00 12,000,000.00 Ya
7. Jalan - Cor Beton/Blok 1,755.00 33,960,000.00 Ya
8. Jalan - Cor Beton/Blok 2,250.00 13,000,000.00 Ya
9. Jalan - Cor Beton/Blok 175.00 3,000,000.00 Ya
10. Jalan - Cor Beton/Blok 620.00 27,000,000.00 Ya
11. Jalan - Cor Beton/Blok 1,225.00 32,000,000.00 Ya
12. Talud 57.60 15,937,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : JETIS WETAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 300.00 12,280,000.00 Ya
3. Drainase, Selokan, SAH, SAL 175.00 17,824,000.00 Ya
4. Drainase, Selokan, SAH, SAL 200.00 6,140,000.00 Ya
5. Drainase, Selokan, SAH, SAL 260.00 6,140,000.00 Ya
6. Jalan - Cor Beton/Blok 750.00 19,606,000.00 Ya
7. Jalan - Cor Beton/Blok 750.00 22,280,000.00 Ya
8. Jalan - Cor Beton/Blok 1,080.00 22,280,000.00 Ya
9. Sanitasi, MCK 1.00 11,188,000.00 Ya
10. Sanitasi, MCK 1.00 5,037,000.00 Ya
11. Talud 389.64 35,225,000.00 Ya
Total   164,000,000.00
Desa / Kelurahan : KALANGAN
1. BOP 1.00 6,000,000.00 Ya
2. Box/Plat Decker 2.00 5,000,000.00 Ya
3. Box/Plat Decker 2.00 5,600,000.00 Ya
4. Drainase, Selokan, SAH, SAL 202.00 49,600,000.00 Ya
5. Jalan - Cor Beton/Blok 352.00 13,800,000.00 Ya
6. Jalan - Cor Beton/Blok 360.00 8,500,000.00 Ya
7. Jalan - Cor Beton/Blok 360.00 8,300,000.00 Ya
8. Jalan - Cor Beton/Blok 516.00 9,000,000.00 Ya
9. Jalan - Cor Beton/Blok 510.00 10,000,000.00 Ya
10. Talud 42.66 16,500,000.00 Ya
11. Talud 20.16 9,000,000.00 Ya
12. Talud 57.00 6,700,000.00 Ya
13. Talud 21.60 8,000,000.00 Ya
14. Talud 54.00 12,000,000.00 Ya
15. Talud 72.00 14,000,000.00 Ya
16. Talud 33.48 6,000,000.00 Ya
17. Talud 49.50 12,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : KALIGAWE
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 79.00 14,460,000.00 Ya
3. Jalan - Cor Beton/Blok 1,660.50 64,231,000.00 Ya
4. Jembatan 2.00 23,018,000.00 Ya
5. Talud 202.00 78,291,000.00 Ya
Total   186,000,000.00
Desa / Kelurahan : KEDEN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 270.00 7,895,000.00 Ya
3. Jalan - Cor Beton/Blok 275.00 8,042,000.00 Ya
4. Jalan - Cor Beton/Blok 150.00 4,386,000.00 Ya
5. Jalan - Cor Beton/Blok 150.00 14,605,000.00 Ya
6. Jalan - Cor Beton/Blok 480.00 14,037,000.00 Ya
7. Jalan - Cor Beton/Blok 59.40 1,737,000.00 Ya
8. Jalan - Cor Beton/Blok 125.00 3,655,000.00 Ya
9. Jalan - Cor Beton/Blok 164.00 4,795,000.00 Ya
10. Jalan - Cor Beton/Blok 120.00 3,509,000.00 Ya
11. Jalan - Cor Beton/Blok 275.00 8,042,000.00 Ya
12. Jalan - Cor Beton/Blok 160.00 4,679,000.00 Ya
13. Jalan - Cor Beton/Blok 205.20 6,000,000.00 Ya
14. Jalan - Cor Beton/Blok 120.00 3,509,000.00 Ya
15. Talud 14.22 4,224,000.00 Ya
16. Talud 49.16 14,605,000.00 Ya
17. Talud 28.44 8,449,000.00 Ya
18. Talud 28.44 8,449,000.00 Ya
19. Talud 28.44 8,449,000.00 Ya
20. Talud 28.44 8,449,000.00 Ya
21. Talud 48.75 14,484,000.00 Ya
Total   158,000,000.00
Desa / Kelurahan : LEMAHIRENG
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 68.00 4,944,000.00 Ya
3. Drainase, Selokan, SAH, SAL 270.00 19,630,000.00 Ya
4. Jalan - Cor Beton/Blok 330.00 9,278,000.00 Ya
5. Jalan - Cor Beton/Blok 444.00 14,329,000.00 Ya
6. Jalan - Cor Beton/Blok 147.50 4,760,000.00 Ya
7. Jalan - Cor Beton/Blok 390.00 10,650,000.00 Ya
8. Jalan - Cor Beton/Blok 271.00 13,119,000.00 Ya
9. Jalan - Cor Beton/Blok 579.00 18,686,000.00 Ya
10. Jalan - Cor Beton/Blok 297.00 12,586,000.00 Ya
11. Jalan - Cor Beton/Blok 250.00 6,454,000.00 Ya
12. Jalan - Cor Beton/Blok 297.00 9,585,000.00 Ya
13. Jalan - Cor Beton/Blok 785.00 18,154,000.00 Ya
14. Jalan - Cor Beton/Blok 330.00 10,650,000.00 Ya
15. Jembatan 1.00 1,316,000.00 Ya
16. Talud 11.80 3,360,000.00 Ya
17. Talud 70.88 18,831,000.00 Ya
18. Talud 70.88 12,961,000.00 Ya
19. Talud 21.60 4,707,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : NGAREN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 100.00 14,325,000.00 Ya
3. Jalan - Cor Beton/Blok 375.00 19,105,000.00 Ya
4. Jalan - Cor Beton/Blok 90.00 4,984,000.00 Ya
5. Jalan - Cor Beton/Blok 220.00 14,523,000.00 Ya
6. Jalan - Cor Beton/Blok 400.00 27,110,000.00 Ya
7. Jalan - Cor Beton/Blok 300.00 25,173,000.00 Ya
8. Jalan - Cor Beton/Blok 385.00 25,173,000.00 Ya
9. Talud 75.00 20,083,000.00 Ya
10. Talud 230.00 23,441,000.00 Ya
11. Talud 175.00 20,083,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : SOBAYAN
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 100.00 10,157,000.00 Ya
3. Drainase, Selokan, SAH, SAL 180.00 11,481,000.00 Ya
4. Drainase, Selokan, SAH, SAL 160.00 10,208,000.00 Ya
5. Drainase, Selokan, SAH, SAL 200.00 12,757,000.00 Ya
6. Drainase, Selokan, SAH, SAL 110.00 11,177,000.00 Ya
7. Drainase, Selokan, SAH, SAL 12.19 9,567,000.00 Ya
8. Jalan - Cor Beton/Blok 44.34 13,173,000.00 Ya
9. Jalan - Cor Beton/Blok 40.00 11,882,000.00 Ya
10. Jalan - Cor Beton/Blok 54.00 10,694,000.00 Ya
11. Jalan - Cor Beton/Blok 36.00 9,090,000.00 Ya
12. Jalan - Cor Beton/Blok 36.00 10,694,000.00 Ya
13. Jalan - Cor Beton/Blok 30.60 16,042,000.00 Ya
14. Talud 40.71 14,325,000.00 Ya
15. Talud 40.70 14,193,000.00 Ya
16. Talud 16.25 14,223,000.00 Ya
17. Talud 40.71 14,337,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : TAMBAKBOYO
1. Bak Kontrol 1.00 2,000,000.00 Ya
2. BOP 1.00 6,000,000.00 Ya
3. Drainase, Selokan, SAH, SAL 553.50 28,191,000.00 Ya
4. Jalan 300.00 15,000,000.00 Ya
5. Jalan - Cor Beton/Blok 1,654.51 107,517,000.00 Ya
6. Talud 200.00 11,600,000.00 Ya
7. Talud 457.00 27,692,000.00 Ya
Total   198,000,000.00
Desa / Kelurahan : TEMUWANGI
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 2,628.00 10,000,000.00 Ya
3. Jalan - Cor Beton/Blok 213.00 5,000,000.00 Ya
4. Jalan - Cor Beton/Blok 367.50 5,000,000.00 Ya
5. Jalan - Cor Beton/Blok 294.00 40,000,000.00 Ya
6. Jalan - Cor Beton/Blok 300.00 10,000,000.00 Ya
7. Jalan - Cor Beton/Blok 660.00 20,000,000.00 Ya
8. Jalan - Cor Beton/Blok 240.00 10,000,000.00 Ya
9. Jembatan 1.00 20,000,000.00 Ya
10. Talud 22.50 34,000,000.00 Ya
11. Talud 114.00 20,000,000.00 Ya
12. Talud 22.20 10,000,000.00 Ya
13. Talud 15.00 6,000,000.00 Ya
14. Talud 11.28 4,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : TROKETON
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 750.00 9,900,000.00 Ya
3. Jalan - Cor Beton/Blok 243.00 9,450,000.00 Ya
4. Jalan - Cor Beton/Blok 3,250.65 78,400,000.00 Ya
5. Jalan - Cor Beton/Blok 180.00 4,800,000.00 Ya
6. Jalan - Cor Beton/Blok 694.00 6,500,000.00 Ya
7. Jalan - Cor Beton/Blok 402.65 6,650,000.00 Ya
8. Jalan - Cor Beton/Blok 278.00 5,900,000.00 Ya
9. Jalan - Cor Beton/Blok 1,050.00 9,900,000.00 Ya
10. Jalan - Cor Beton/Blok 266.00 7,450,000.00 Ya
11. Talud 45.00 11,450,000.00 Ya
12. Talud 48.00 8,000,000.00 Ya
13. Talud 40.00 11,950,000.00 Ya
14. Talud 12.76 3,400,000.00 Ya
15. Talud 52.00 6,500,000.00 Ya
16. Talud 37.50 4,300,000.00 Ya
17. Talud 25.20 5,350,000.00 Ya
18. Talud 15.17 4,100,000.00 Ya
Total   200,000,000.00
Kota : KULON PROGO
Kecamatan : GALUR
Desa / Kelurahan : BROSOT
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 3,810.00 157,080,000.00 Ya
3. Sanitasi, MCK 4.00 18,000,000.00 Ya
4. Talud 1.00 4,920,000.00 Ya
Total   186,000,000.00
Kecamatan : LENDAH
Desa / Kelurahan : JATIREJO
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 2,000.00 5,000,000.00 Ya
3. Gorong-Gorong 1,398.00 2,279,000.00 Ya
4. Jalan - Cor Beton/Blok 4,279.00 111,131,000.00 Ya
5. Sanitasi, MCK 4.00 6,230,000.00 Ya
6. Talud 425.00 69,360,000.00 Ya
Total   200,000,000.00
Kecamatan : SENTOLO
Desa / Kelurahan : SALAMREJO
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 375.00 11,370,000.00 Ya
3. Jalan - Cor Beton/Blok 500.00 21,485,000.00 Ya
4. Jalan - Paving Blok 550.00 24,145,000.00 Ya
5. Sanitasi, MCK 16.00 137,000,000.00 Ya
Total   200,000,000.00
Kota : SLEMAN
Kecamatan : DEPOK
Desa / Kelurahan : CATUR TUNGGAL
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 2,000.00 138,500,000.00 Ya
3. Jalan - Paving Blok 400.00 17,500,000.00 Ya
4. Sumur Resapan, SPAH 90.00 38,000,000.00 Ya
Total   200,000,000.00
Kecamatan : GAMPING
Desa / Kelurahan : AMBARKETAWANG
1. Jalan 1,375.00 45,687,500.00 Ya
2. Jalan - Cor Beton/Blok 379.70 44,404,250.00 Ya
3. Jalan - Paving Blok 120.00 34,980,000.00 Ya
4. Talud 231.61 44,404,250.00 Ya
5. Tutup Saluran 6.00 10,524,000.00 Ya
Total   180,000,000.00
Desa / Kelurahan : BALECATUR
1. Jalan 1,800.00 180,000,000.00 Ya
2. Talud 137.00 20,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : BANYURADEN
1. Gorong-Gorong 15.00 1,689,800.00 Ya
2. Jalan 702.00 20,802,780.00 Ya
3. Jalan - Paving Blok 4,260.00 112,238,400.00 Ya
4. Talud 168.00 65,269,020.00 Ya
Total   200,000,000.00
Desa / Kelurahan : NOGOTIRTO
1. Jalan 1,290.00 21,000,000.00 Ya
2. Jalan - Paving Blok 600.00 42,250,000.00 Ya
3. Jembatan 1.00 15,750,000.00 Ya
4. Sumur Resapan, SPAH 27.00 27,000,000.00 Ya
5. Talud 312.80 64,000,000.00 Ya
Total   170,000,000.00
Desa / Kelurahan : TRIHANGGO
1. BOP 1.00 6,000,000.00 Ya
2. Sumur Resapan, SPAH 194.00 194,000,000.00 Ya
Total   200,000,000.00
Kecamatan : GODEAN
Desa / Kelurahan : SIDOAGUNG
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 336.00 51,500,000.00 Ya
3. Jalan 3,050.00 35,000,000.00 Ya
4. Jalan - Cor Beton/Blok 360.00 31,000,000.00 Ya
5. Jalan - Paving Blok 1,060.00 13,000,000.00 Ya
6. Talud 2,352.00 63,500,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : SIDOMOYO
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Cor Beton/Blok 810.00 63,731,000.00 Ya
3. Jalan - Paving Blok 1,390.00 17,160,000.00 Ya
4. Jalan - Sand Sheet 2,835.00 113,109,000.00 Ya
Total   200,000,000.00
Kecamatan : KALASAN
Desa / Kelurahan : TAMAN MARTANI
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 350.00 4,000,000.00 Ya
3. Jalan 3,000.00 145,500,000.00 Ya
4. Jalan - Cor Beton/Blok 6,745.00 10,500,000.00 Ya
Total   166,000,000.00
Desa / Kelurahan : TIRTO MARTANI
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 4,442.00 164,500,000.00 Ya
3. Jalan - Cor Beton/Blok 688.00 17,000,000.00 Ya
4. Jalan - Paving Blok 244.00 12,500,000.00 Ya
Total   200,000,000.00
Kecamatan : MLATI
Desa / Kelurahan : TIRTOADI
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 800.00 43,500,000.00 Ya
3. Jalan - Cor Beton/Blok 2,950.00 35,000,000.00 Ya
4. Jalan - Paving Blok 3,680.00 69,000,000.00 Ya
5. Talud 1,470.00 46,500,000.00 Ya
Total   200,000,000.00
Kecamatan : PRAMBANAN
Desa / Kelurahan : BOKO HARJO
1. BOP 1.00 6,000,000.00 Ya
2. Drainase, Selokan, SAH, SAL 215.00 60,300,000.00 Ya
3. Gorong-Gorong 4.50 3,300,000.00 Ya
4. Jalan 600.00 71,000,000.00 Ya
5. Jalan - Cor Beton/Blok 2,908.00 17,100,000.00 Ya
6. Talud 244.00 42,300,000.00 Ya
Total   200,000,000.00
Kecamatan : SEYEGAN
Desa / Kelurahan : MARGOAGUNG
1. BOP 1.00 6,000,000.00 Ya
2. Gorong-Gorong 8.00 14,052,700.00 Ya
3. Jalan - Paving Blok 2,870.00 58,200,000.00 Ya
4. Jembatan 2.00 57,716,500.00 Ya
5. Sanitasi, MCK 2.00 21,350,800.00 Ya
6. Talud 60.00 42,680,000.00 Ya
Total   200,000,000.00
Kecamatan : TURI
Desa / Kelurahan : DONOKERTO
1. Air Bersih, Reservoar, Broncapturing 12.00 40,999,500.00 Ya
2. BOP 1.00 6,000,000.00 Ya
3. Instalasi Air Bersih 5,650.00 122,340,500.00 Ya
4. Jalan - Paving Blok 1,095.00 30,660,000.00 Ya
Total   200,000,000.00
Kota : YOGYAKARTA
Kecamatan : GONDOKUSUMAN
Desa / Kelurahan : BACIRO
1. Instalasi Air Bersih 450.00 161,000,000.00 Ya
2. Jalan - Paving Blok 1,789.00 26,000,000.00 Ya
3. Sumur Resapan, SPAH 4.00 13,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : DEMANGAN
1. Irigasi 193.00 65,000,000.00 Ya
2. Jalan 516.00 62,000,000.00 Ya
3. Jalan - Paving Blok 427.00 39,000,000.00 Ya
4. Sanitasi, MCK 1.00 28,300,000.00 Ya
5. Sumur Resapan, SPAH 1.00 5,700,000.00 Ya
Total   200,000,000.00
Kecamatan : GONDOMANAN
Desa / Kelurahan : PRAWIRODIRJAN
1. Jalan - Paving Blok 1,250.00 60,000,000.00 Ya
2. Sanitasi, MCK 16.00 120,000,000.00 Ya
3. Sumur Resapan, SPAH 5.00 20,000,000.00 Ya
Total   200,000,000.00
Kecamatan : KOTAGEDE
Desa / Kelurahan : PRENGGAN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Paving Blok 4,360.00 194,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : PURBAYAN
1. BOP 1.00 6,000,000.00 Ya
2. Gorong-Gorong 160.00 125,500,000.00 Ya
3. Jalan - Paving Blok 500.00 55,700,000.00 Ya
4. Sumur Resapan, SPAH 13.00 12,800,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : REJOWINANGUN
1. BOP 1.00 6,000,000.00 Ya
2. Jalan - Paving Blok 1,380.00 107,128,000.00 Ya
3. Sumur Resapan, SPAH 22.00 21,149,500.00 Ya
4. Talud 178.50 65,722,500.00 Ya
Total   200,000,000.00
Kecamatan : KRATON
Desa / Kelurahan : PANEMBAHAN
1. Gorong-Gorong 60.00 40,000,000.00 Ya
2. Jalan - Paving Blok 1,013.00 42,000,000.00 Ya
3. Sanitasi, MCK 4.00 50,000,000.00 Ya
4. Sumur Resapan, SPAH 52.00 45,000,000.00 Ya
5. Sumur Suntik 1.00 23,000,000.00 Ya
Total   200,000,000.00
Kecamatan : MANTRIJERON
Desa / Kelurahan : GEDONGKIWO
1. Balai Pertemuan 3.00 69,520,000.00 Ya
2. BOP 1.00 6,000,000.00 Ya
3. Jalan 12.30 6,080,000.00 Ya
4. Jalan - Cor Beton/Blok 1,235.50 76,230,000.00 Ya
5. Sanitasi, MCK 1.00 15,170,000.00 Ya
6. Talud 13.50 27,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : MANTRIJERON
1. BOP 1.00 6,000,000.00 Ya
2. Jalan 1,365.00 194,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : SURYODININGRATAN
1. Balai Pertemuan 8.00 47,062,190.00 Ya
2. BOP 1.00 6,000,000.00 Ya
3. Drainase, Selokan, SAH, SAL 75.00 25,882,480.00 Ya
4. Jalan 300.00 25,424,500.00 Ya
5. Jalan - Paving Blok 650.00 58,259,480.00 Ya
6. Jembatan 1.00 10,703,290.00 Ya
7. Penampung Air Hujan, Embung 17.00 16,521,290.00 Ya
8. Sanitasi, MCK 1.00 10,146,770.00 Ya
Total   200,000,000.00
Kecamatan : MERGANGSAN
Desa / Kelurahan : BRONTOKUSUMAN
1. Balai Pertemuan 1.00 52,228,800.00 Ya
2. Balai Pertemuan 1.00 53,375,200.00 Ya
3. BOP 1.00 6,000,000.00 Ya
4. Gorong-Gorong 610.00 19,567,000.00 Ya
5. Jalan 957.00 25,232,000.00 Ya
6. Talud 176.00 43,597,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : KEPARAKAN
1. Bak Kontrol 21.00 23,000,000.00 Ya
2. BOP 1.00 6,000,000.00 Ya
3. Jalan - Paving Blok 875.60 56,914,000.00 Ya
4. Other 51.50 11,000,000.00 Ya
5. Penampung Air Hujan, Embung 15.00 19,500,000.00 Ya
6. Sanitasi, MCK 6.00 63,311,000.00 Ya
7. Sumur Resapan, SPAH 207.00 15,525,000.00 Ya
8. Tutup Saluran 51.00 4,750,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : WIROGUNAN
1. Balai Pertemuan 9.00 65,000,000.00 Ya
2. BOP 1.00 6,000,000.00 Ya
3. Gorong-Gorong 424.00 57,000,000.00 Ya
4. Jalan 477.00 51,000,000.00 Ya
5. Sumur Resapan, SPAH 11.00 21,000,000.00 Ya
Total   200,000,000.00
Kecamatan : TEGALREJO
Desa / Kelurahan : TEGALREJO
1. Drainase, Selokan, SAH, SAL 156.30 200,000,000.00 Ya
Total   200,000,000.00
Kecamatan : UMBULHARJO
Desa / Kelurahan : GIWANGAN
1. Drainase, Selokan, SAH, SAL 500.00 200,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : MUJA MUJU
1. Balai Pertemuan 1.00 200,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : PANDEYAN
1. BOP 1.00 5,129,384.00 Ya
2. Gorong-Gorong 334.00 71,964,292.00 Ya
3. Jalan 1,131.00 32,432,226.00 Ya
4. Jalan - Paving Blok 795.00 60,873,154.00 Ya
5. Sumur Resapan, SPAH 34.00 29,600,944.00 Ya
Total   200,000,000.00
Desa / Kelurahan : SEMAKI
1. Jalan - Paving Blok 4,000.00 200,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : SOROSUTAN
1. BOP 1.00 5,068,605.00 Ya
2. Instalasi Air Bersih 232.88 106,275,752.00 Ya
3. Jalan - Paving Blok 758.50 49,655,643.00 Ya
4. Sumur Resapan, SPAH 65.00 39,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : TAHUNAN
1. Gorong-Gorong 150.00 70,000,000.00 Ya
2. Jalan 300.00 130,000,000.00 Ya
Total   200,000,000.00
Desa / Kelurahan : WARUNGBOTO
1. Drainase, Selokan, SAH, SAL 134.00 133,257,000.00 Ya
2. Jalan 410.00 66,743,000.00 Ya
Total   200,000,000.00

Copyright Rekompakjrf © 2007